LOCAL planners have approved plans to to build up to 277 wind turbines in an area of sea off the Caithness coast more than twice the size of Dundee.
The biggest turbines will be eight miles offshore and at least twice the size of Edinburgh's 197ft Scott Monument.
Members of Highland Council agreed the £3 billion Beatrice offshore wind-farm project should go ahead without any dissent during a planning meeting and it will be passed to ministers for a final decision.
The independent nationalist councillor for Caithness Landward, Alex Macleod, said: "The importance of getting this process right for the far north cannot be overstated.
"The project will put the far north on the map as the destination to invest at the moment in renewable energy."
He said the project will reap benefits for the Nigg fabrication yard and Wick Harbour.
Councillor Macleod added: "This is a golden opportunity to develop Wick harbour as the destination to service and maintain not just this development, but other future offshore developments. With a harbour, a hospital and an airport it is perfectly situated."
The Scottish Government had sought the council's views on the scheme, a partnership between SSE Renewables and Repsol Nuevas Energias UK, which will generate 1000 megawatts.
Wick and Nigg are identified as likely service centres along with Ardersier if it is developed. It is hoped the project will give Caithness a post-Dounreay future and which could see the far north replace Aberdeen as an investment hub.
Ministers are also to decide on another project consisting of up to 339 turbines across three offshore wind farms further out in the Moray Firth.
Meanwhile, East Lothian's planning commitee has granted planning consent for works to connect the Neart na Gaoithe offshore wind farm. It gave the go ahead for around seven miles of buried cable between Thorntonloch Beach, East Lothian, where the subsea cable is planned to reach shore, and Crystal Rig onshore wind farm in the Lammermuir Hills, where the Grid connection would be made.
l A single wind turbine which can be seen from the late Queen Mother's Caithness holiday home where Prince Charles still visits has been approved by Highland councillors.
The turbine on Barrogill Mains farm will be a around 500 yards away from the Castle of Mey. The farmer had previously been refused permission for a wind turbine.
Why are you making commenting on The Herald only available to subscribers?
It should have been a safe space for informed debate, somewhere for readers to discuss issues around the biggest stories of the day, but all too often the below the line comments on most websites have become bogged down by off-topic discussions and abuse.
heraldscotland.com is tackling this problem by allowing only subscribers to comment.
We are doing this to improve the experience for our loyal readers and we believe it will reduce the ability of trolls and troublemakers, who occasionally find their way onto our site, to abuse our journalists and readers. We also hope it will help the comments section fulfil its promise as a part of Scotland's conversation with itself.
We are lucky at The Herald. We are read by an informed, educated readership who can add their knowledge and insights to our stories.
That is invaluable.
We are making the subscriber-only change to support our valued readers, who tell us they don't want the site cluttered up with irrelevant comments, untruths and abuse.
In the past, the journalist’s job was to collect and distribute information to the audience. Technology means that readers can shape a discussion. We look forward to hearing from you on heraldscotland.com
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules hereComments are closed on this article