Warning over MoD aircraft delays and cost

BRITAIN'S armed forces are facing critical shortfalls in air transport and air-to-air refuelling capabilities because of delays in delivering new aircraft, Whitehall's spending watchdog has warned.

In its annual report on the Ministry of Defence's major equipment projects, the National Audit Office said overruns on the 16 biggest defence programmes meant costs had gone up during the past year by £468 million and, since they were approved, by £6.6 billion. Delays total 39 years.

The report disclosed that delays to the £32m Falcon communications system, which was developed for use in Afghanistan, meant it would not now be ready until after British troops have withdrawn in 2014.

Margaret Hodge, chairwoman of the Commons Public Accounts Committee which oversees the NAO, said: "Yet again, the MoD's annual report card has found unacceptable cost increases and delays."

Jim Murphy, Shadow Defence Secretary, said: "Less than a year after Philip Hammond (Defence Secretary) claimed to have balanced the budget, waste and delay are characteristics of his equipment programme."

Mr Hammond insisted "rigorous financial management" by the UK Government had reduced the annual cost growth of the biggest projects.

Contextual targeting label: 
Finance

Commenting & Moderation

We moderate all comments on HeraldScotland on either a pre-moderated or post-moderated basis.
If you're a relatively new user then your comments will be reviewed before publication and if we know you well and trust you then your comments will be subject to moderation only if other users or the moderators believe you've broken the rules

Moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours. Please be patient if your posts are not approved instantly.

134616