LIGHTNING, a bird strike or a stray branch falling on to a main power transmission line may have been responsible for power cuts that blacked out almost half of the land mass of Scotland.
Investigators are also examining whether Wednesday night's loss of power to 205,000 homes may have been the result of a flashover, when power comes out of the conductor and is earthed. Vandalism and metal theft have been ruled out.
A helicopter and ground crews were all involved as SSE sought to understand the cause of the power cut, which is thought to be unprecedented in terms of the size of the area it affected.
The 55-mile stretch of power lines between Blackhillock substation near Keith in Moray and Knocknagael south of Inverness was quickly identified as the likely location of the fault that caused the outage.
But SSE said it could not give a detailed explanation of why this had led to the blackouts across the north of Scotland at 8.30pm.
Industry sources are surprised, as back-up protection would normally be expected to ensure a quick restoration of power.
The failure spread across Moray, the Highlands from Fort William to Caithness, Skye, the Western Isles and Orkney.
However, more than half of homes were reconnected by 10.30pm, with 95,000 customers still off, but this dropped to 25,000 by 11pm and all were restored by 12.30am.
Inverness was off for less than half an hour, while in parts of Skye it was an hour-and-a-half and for some homes on the Black Isle, just 20 miles from Inverness, it was two-and-a-half hours.
The national grid is like a huge system of water pipes that must be kept at the same pressure. Minute by minute it has to balance out the electricity being supplied to the system -by generators such as power stations hydro schemes and wind farms -with the fluctuating levels of demand from customers.
An SSE spokesman explained: "The grid network is technologically advanced, so if it thinks it is in distress or there is a fault, it will trip pretty much as your house would trip if something is wrong. It does this to protect equipment."
He said all the lines were inter-connected, so the lines around the rest of Highlands and Islands had also tripped out because this advanced circuitry technology "had warned something was wrong. But the warning equipment on the rest of the grid had not reacted in this way, so hadn't tripped."
First Minister Alex Salmond, who was in Stornoway at the time, chaired a meeting of the government's resilience committee. He said the plans in place had made sure there was no major problem.
Why are you making commenting on The Herald only available to subscribers?
It should have been a safe space for informed debate, somewhere for readers to discuss issues around the biggest stories of the day, but all too often the below the line comments on most websites have become bogged down by off-topic discussions and abuse.
heraldscotland.com is tackling this problem by allowing only subscribers to comment.
We are doing this to improve the experience for our loyal readers and we believe it will reduce the ability of trolls and troublemakers, who occasionally find their way onto our site, to abuse our journalists and readers. We also hope it will help the comments section fulfil its promise as a part of Scotland's conversation with itself.
We are lucky at The Herald. We are read by an informed, educated readership who can add their knowledge and insights to our stories.
That is invaluable.
We are making the subscriber-only change to support our valued readers, who tell us they don't want the site cluttered up with irrelevant comments, untruths and abuse.
In the past, the journalist’s job was to collect and distribute information to the audience. Technology means that readers can shape a discussion. We look forward to hearing from you on heraldscotland.com
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules hereComments are closed on this article